Detailed design of piping, equipment, E&I and minor civils.
Import Terminal with 17,600 m³ mounded LPG storage in four tanks,
marine unloading facilities, LPG pipeline, road tanker loading facilities,
building, utilities etc. The four tanks were unmounded in Germany and
shipped to Mombasa.